HP Performance-Optimized Datacenter, 12 m (40 ft) Site Requirements Information Part Number 513171-002 March 2010 (Second Edition)
HP POD specifications 10 Water input side view Callout Feature 1 CWR/CWS portal 2.7 m (9 ft) 2 IT cable portals 2 m (7 ft) 3 Central facility
HP POD specifications 11 External hot aisle view Water supply specifications Feature Specification Facility input temperature to HP POD 12º to
Water quality requirements 12 Water quality requirements Water quality requirements and specifications • Closed-loop water must not contain any lim
Water quality requirements 13 Piping materials Do not use the following interconnecting piping materials in a closed water system: • Oxidizing bioc
Power management 14 Power management Connection requirements When determining the final location of your power and water connections, consider the d
Power management 15 Standard density HP POD with redundant power Component Quantity Phases Amps Volts Description Primary feeders 2 3 225
Power management 16 High density HP POD The high density HP POD must be supplied with six feeders. • 3-phase • 380 to 415V wye connected • 50 to
Power management 17 Component Quantity Phases Amps Volts Description the HP POD. Primary feeders 3 3 225 415/240 Supply power path to IT e
Supported facility connections 18 Supported facility connections Humidifier specifications A dedicated supply of domestic water is required if the o
Supported facility connections 19 IMPORTANT: For full protection, you must ground the HP POD, power distribution components and the water distribu
© Copyright 2009, 2010 Hewlett-Packard Development Company, L.P. The information contained herein is subject to change without notice. The only warr
Supported facility connections 20 The HP POD ECS offers: • The ability to monitor the status of water and air temperatures, water pressures, and wa
Acronyms and abbreviations 21 Acronyms and abbreviations ASSD air sampling smoke detector BMS building management system ECS environmental control
Contents Site requirements ...
Site requirements 4 Site requirements About this document This document outlines the installation requirements for a 12 m (40 ft) HP POD. These guid
Site requirements 5 • You have chilled water at your final location. • You have made provisions for properly grounding the HP POD. System utiliti
Site requirements 6 Drainage Item Component 1 Heat exchanger condensate drains 2 Water main supply/return drain 3 Humidifier drain Optional
Site requirements 7 Features Specifications temperature* Operating humidity • 0% to 100% relative noncondensing Non-operating humidity* • 5 to 95
HP POD specifications 8 HP POD specifications Dimensions The HP POD is approximately 12.2 m (40 ft) long, 2.4 m (8 ft) wide, and 2.9 m (9.5 ft) tall
HP POD specifications 9 Item Component 4 Fan control panel 5 Redundant relay panel 6 House panels 7 Main input power junction boxes 8 Security